07/12/2011

Key Dates Announced For Edinburgh Tram Programme

The city of Edinburgh council has outlined details of its overall client target programme which identifies the last remaining major milestones for the city’s tram project.

The Council also reaffirmed its commitment to working with the public and affected businesses in advance of tram delivery to minimise the impact of construction activity.

The remaining works will take place between now and the expected completion date of summer 2014.

Councillor Gordon Mackenzie, Transport Convenor said: "The project has been progressing well since work restarted earlier this year and we are now in a position to look to the future with greater clarity and positivity. We want to share this information with affected businesses, the public and other interested parties so they can have an understanding of just what work is left to be done and when we will be going in and completing it.

-- Advertisement --
NorthernAsbestosServicesLtd

"We will be working with businesses and residents who live in the affected areas in advance of and throughout the works to make sure we can deliver this new service for the city on target for summer 2014."

Director of City Development at the City of Edinburgh Council, Dave Anderson, added: "Good progress has been made since work recommenced in September and we are now able to provide the overall client target programme which will help inform businesses and affected parties to plan ahead.

"We fully recognise the important contribution all the affected businesses make to the capital's economy which is why we want to renew our pledge that when information about work on specific sites is available we will share this as widely as possible. We want to ensure people are informed and updated regularly throughout the remainder of the works.

"The Council has committed nearly £1 million of support in our Open for Business budget for this year and next. The aim of this money is to support affected businesses and minimise disruption while this key transport project is being delivered."

(GK)

Latest Construction News

02/05/2024

Malin Group has secured planning permission in principle for its proposed development of the Scottish Marine Technology Park (SMTP). Malin Group's vision for the site is to deliver a state-of-the-art marine excellence hub which will bring together manufacturers with marine and renewables ...
02/05/2024

Fleming Building has officially broken ground on the development of the multi-million pound Bishopton Dargavel Satellite Facility. Working alongside Hub West Scotland and NHS Greater Glasgow & Clyde through a detailed pre-construction period, designs were developed to meet a range of requirements ...
02/05/2024

Aberdeenshire Council has announced the installation of a downstream defender as part of ongoing works to restore and improve the ponds at Denman Park in Westhill. The popular ponds in Denman Park are home to a wide variety of pondlife and wildlife but have been subject to pollution from a range ...
02/05/2024

Contractors RJ McLeod are on schedule to complete the construction of a new Largs seawall in North Ayrshire. The £4.6m project is almost complete with the northern section of the promenade expected to re-open to pedestrians before the summer season gets under way. The project has seen the ...
02/05/2024

Scottish Water has announced the successful completion of a major technological transformation of Glasgow's Victorian era Partick Pumping Station. Built some 120 years ago, the pumping station remains a key part of the city's waste water infrastructure and still serves 170,000 people. It is one of ...
02/05/2024

SSEN Transmission has committed to consider community and landowner proposed alignments as part of its Kintore-Tealing 400kV project. These alignments - which will be assessed in parallel with other alignment options within the refined routes SSEN Transmission recently consulted on - are around ...
02/05/2024

SSEN Distribution has announced that it has chosen Electron's 'ElectronConnect' platform to streamline and expand its procurement of Flexibility Services. The company's DSO Acceleration Action Plan identified the selection of a new Flexibility Market Platform during the Spring of 2024 as a key ...
02/05/2024

West Dunbartonshire Council has declared a housing emergency, highlighting the unprecedented pressures on the ability to meet the needs of those in social housing or seeking a Council property. Councillor Gurpreet Singh Johal, who is the Convener of Housing and Communities, made the declaration ...
02/05/2024

The Highland Council has submitted its response to the Scottish Government's consultation on Masterplan Consent Areas (MCA), developed by members of the Economy and Infrastructure Committee. The Scottish Government is proposing the introduction of discretionary powers to establish Masterplan ...
02/05/2024

As part of its ongoing efforts to improve biodiversity across the region, Perth and Kinross Council has announced an extension of its Grassland Management Trials, following successes at 42 other sites. These areas of longer grass will create space for nature and help attract bees, butterflies and ...
RBT Underfloor LimitedRBT Underfloor LimitedMorris & Spottiswood LtdFair City Precast LtdRural House LtdCoastworksIMS Heat PumpsE & P BricklayingStuart King Architecture & Design LtdStuart King Architecture & Design Ltd (Acoustic)
Terms and Conditions
2024/05/02 16:48:45